City of Čačak:
Construction of gas distribution network of low-pressure up to 4 bar (GDN)
– gas distribution network of low-pressure up to 4 bar in 110 km length – constructed and went into operation,
–2 Metering and Regulating Stations (MRS) – constructed and went into operation,
– completion of construction date: 2007.
Municipality of Bač:
Construction of gas distribution network of low-pressure up to 4 bar (GDN) and gas distribution network of medium-pressure up to 16 bar (GD) with the corresponding MRS
– gas distribution network of low-pressure up to 4 bar (GDN) in 170 km length – constructed and ready to go into operation,
– gas distribution network of medium-pressure up to 16 bar (GD) in 20 km length – constructed and ready to go into operation,
–4 Metering and Regulating Stations (MRS) – constructed and ready to go into operation,
– completion of construction date: 2015.
The town of Požarevac:
Construction of gas distribution network of low-pressure up to 4 bar (GDN) and gas distribution network of medium-pressure up to 16 bar (GD) with the corresponding MRS
– gas distribution network of low-pressure up to 4 bar (GDN) in 260 km length – constructed and ready to go into operation,
– gas distribution network of medium-pressure up to 16 bar (GD) in 54 km length – constructed and ready to go into operation,
–10 Metering and Regulating Stations (MRS) – constructed and ready to go into operation,
– planned date for the whole network to go into operation: mid 2017.
Branicevo District
Works on gasification of Branicevo district are underway.
The planned completion of construction in the territory of the Branicevo district is in 2020.